DYNAMIC LOAD TEST ON DRIVEN PILE (PDA TEST)
This
method statement describes the typical dynamic load test on driven pile (PDA
Test) procedure. Dynamic pile testing is performed by well-trained and
experienced engineers using a Pile Driving Analyzer (PDA) at site and pile wave
analysis will be carried out on the signal acquired by using Case Pile Wave
Analysis Program (CAPWAP).
Plant
and Equipment
The plant /
equipment to be used for the works shall comprise of the following:
§ PDI
series pile driving analyzer and CAPWAP analysis program to determine the
mobilized capacity of a test pile. Pile Driving Analyzer shall comprise;
·
Pile
Driving Analyzer
·
2
Strain Transducers
·
2
Accelerometers
·
1-4
Cable
·
30m
Extension Cable
The combination of
the calibrated sensors and the latest analysis program provides a high accuracy
and reliable test results.
Dynamic Load Test
Preparation
·
Prior
to lifting the pile to be dynamically tested, the Contractor shall provide a
minimum of 3 ft (1 m) clear access to 180 degree opposite faces of the pile for
pile preparation.
·
The
test pile must be exposed at least 1 meter above the existing ground level to
avoid any obstruction endangering the sensors or cable during testing.
·
All
pre-cast concrete pile must remain uncut for restrike purpose and an
appropriate piling hammer is required for testing purpose until the final
result is obtained.
·
Most
of all, the safety of the test personal shall be ensured.
Testing Procedures
- Drilling 3 appropriate sizes of holes on both side of a test pile (figure 1). The purpose is to obtain the eccentricity in order to eliminate hammer alignment effect.
- Two strain transducers and two accelerometers will then attach to the pile at least at a distance of 2 times diameter of the pile or 1.0m from the pile head (whichever comes first) during initial driving or restrike testing (Figure 2). Stress wave generated by hammer impact on pile top will be recorded in terms of force and acceleration.
- The signal captured will be presented in a graph as force curve and velocity curve and is stored in the pile driving analyzer for later analysis purpose
Result Interpretation and Analysis
·
By computation from the pile
driving analyzer on force and velocity curve recorded, a lot of useful
information can be provided on site as preliminary results. These results
include:
o Pile
capacity at the time of testing by CASE method. (RMX)
§ Capacity
predicted by assuming appropriate soil damping factor (Jc), young modulus (Em)
and wave speed (Ws).
o Pile
top compression stress during pile driving.
§ In
order to limit the possibility of pile top damage at the time of testing, pile
top stress must be kept within certain bounds. It can be derived by taking
maximum force applied to the pile top (FMX) divided by cross sectional area of
the pile.
§
A representative blow will
be selected for further analysis seeking for:
·
Mobilized capacity using
CAPWAP signal matching program.
·
Load vs. settlement graph
similar to static load test.
·
Portion by portion skin
friction distributed at pile shaft.
·
End bearing at the pile toe.
·
Hammer efficiency.
·
Integrity at the pile.
Ulasan
Catat Ulasan